Planning tool

# Developer land workplan

The order of work from screening a site to closing on it

This workplan sets out the order of work a developer follows from screening a site to closing on it: site control, title, survey, environmental and geotechnical studies, utilities, access, approvals, fees and financing. Each step says who to ask and what to request. It is a process guide, not legal or engineering advice.

In short: A developer workplan from site screening to closing: title, survey, environmental and geotechnical studies, utilities, access, approvals and financing.

## Which items apply to you?

Property typeAll property typesResidential subdivisionInfill or single parcelWaterfront or lakefront land

StateAll statesTennesseeFlorida

Copy as text

Print

Clear ticks

**Nothing you tick or choose is saved or sent.** The list runs in your browser. Use Copy as text or Print to keep your own copy. This is a process guide, not legal, engineering, tax or insurance advice, and October 18, 2026 is the date its sources were read.

## Screen and control the site

1.  Screen the site with the public-source readings

    Flood zone, wetlands, soil, slope, drainage and land cover narrow which sites deserve diligence money.

    Ask  
    No one yet. This is background, not a determination.

    [Read the public-source readings for the address](https://abodeintlrealty.com/property-research/lookup/)

2.  Control the site on terms that give you time

    A contract or option needs a diligence period long enough to finish the studies below, and a right to leave if one fails.

    Ask  
    Your real estate attorney.

    Request  
    A contract with a diligence period, extension rights, and deposit terms your attorney has read.

3.  Order the title commitment and read every exception

    Easements, covenants, liens, mineral and access rights can each change what is possible.

    Ask  
    Title company and attorney.

    Request  
    Title commitment with exception documents and the plat.

4.  Order a boundary and topographic survey

    Boundaries, easements, topography and encroachments set the design envelope. For lender and title use, ask which survey standard is required.

    Ask  
    A licensed land surveyor and your title company.

    Request  
    A survey to the standard your lender and title company require.

## Diligence

1.  Commission a Phase I environmental site assessment

    A Phase I shows past uses and recognized environmental conditions. A standard recognized under EPA’s All Appropriate Inquiries rule matters for liability protection, so ask the consultant and your attorney.

    Ask  
    An environmental consultant and your attorney.

    Request  
    A Phase I report prepared to the current standard, dated within the window your lender and attorney need.

    [Source: Winston & Strawn, EPA approves ASTM E1527-21 as meeting All Appropriate Inquiries (effective February 13, 2023)](https://winston.com/en/winston-and-the-legal-environment/its-official-epa-approves-phase-i-standard-astm-e1527-21-as-meeting-all-appropriate-inquiry-effective-february-13-2023.html)

2.  Get geotechnical borings

    Soil conditions drive foundation type, grading cost and whether the plan holds.

    Ask  
    A geotechnical engineer.

    Request  
    A report with boring logs and foundation and pavement recommendations.

3.  Delineate wetlands and streams, and ask about protected species

    Wetlands, streams and protected species can limit developable area and add federal and state steps.

    Ask  
    A wetland consultant; the U.S. Army Corps of Engineers; the state environmental agency; the U.S. Fish and Wildlife Service.

    Request  
    A delineation report, any jurisdictional determination and a species screening letter.

4.  Check the floodplain and downstream drainage

    Mapped flood hazard areas and the way water leaves the site decide lot yield and stormwater design.

    Ask  
    The floodplain administrator and a civil engineer.

    Request  
    The flood zone and base flood elevation, and a drainage study scope.

    [Source: FEMA Map Service Center](https://msc.fema.gov/portal/home)

5.  Get will-serve letters for utilities

    Capacity and extension cost for water, sewer, power, gas and telecom can decide the project.

    Ask  
    Each utility.

    Request  
    Written availability, capacity, tap or impact fees, and the cost of any extension.

6.  Confirm access, frontage and traffic requirements

    The site needs approved access, and a project of size may need a traffic study or road improvements.

    Ask  
    The county or state road authority and the planning office.

    Request  
    Driveway or road approval requirements and any traffic study threshold.

7.  For waterfront land, check shoreline and dock rules

    Shoreline buffers, docks and seawalls can need separate approvals that run on their own clocks.

    Ask  
    The agency that controls the shoreline and the city or county.

    Request  
    Written rules and approval steps for the parcel.

    For: Waterfront or lakefront land

    [Florida oceanfront due diligence](https://abodeintlrealty.com/guides/florida-oceanfront-due-diligence/) [Tennessee acreage due-diligence guide](https://abodeintlrealty.com/guides/tennessee-acreage-due-diligence/)

## Entitlement and approvals

1.  Hold a pre-application meeting

    Planning staff can say which approvals your plan needs and in what order.

    Ask  
    The planning office.

    Request  
    A written summary of required approvals, hearings and submission checklists.

2.  Map the approval path

    Rezoning, subdivision plat, site plan and planned development each have their own steps, hearings and timelines. Plan around the office’s published calendar.

    Ask  
    The planning office and your land-use attorney.

    Request  
    A written approval path with each hearing date and the office’s published review times.

3.  List impact fees, tap fees and bonds

    Fees and bonds due at plat or permit can change the pro forma.

    Ask  
    The planning, building and utility offices.

    Request  
    Current fee schedules and bond requirements in writing.

## Financing and closing

1.  Ask the lender what it needs

    Appraisal, environmental, geotechnical, survey, entitlement status and entity documents are common conditions.

    Ask  
    Your lender.

    Request  
    A written condition list with deadlines.

2.  Calendar every deadline from the contract

    The diligence period, extensions, approvals and closing date have dates that cost money if missed.

    Ask  
    Your attorney.

    Request  
    A single dated calendar of contract deadlines.

3.  Plan the first 90 days after closing

    Permits, bonds, erosion control, contractor selection and insurance each need lead time.

    Ask  
    Your civil engineer and general contractor.

    Request  
    A short written start plan with owners and dates.

## How should you use this checklist?

- **Treat each “Ask” as a real person.** A licensed professional or an office decides each question. The checklist only tells you whom to ask and what to request.
- **Get answers in writing.** A letter, a permit, a report or a recorded document is evidence. A phone answer is not.
- **Read the public-source readings first.** Run the [address lookup](https://abodeintlrealty.com/property-research/lookup/) to see flood zone, wetlands, soil, elevation, slope, drainage and land cover for a site. Each reading is context at one point, not a determination.
- **Run the numbers.** The [development pro forma worksheet](https://abodeintlrealty.com/tools/development-pro-forma-worksheet/) adds up the costs from figures you type.
- **Plan the funding.** The [draw schedule worksheet](https://abodeintlrealty.com/tools/draw-schedule-worksheet/) shows how equity and a loan would fund costs month by month, from figures you type.
- **Rules change.** Sources were read October 18, 2026. Confirm the current rule with the named office or your attorney.

More checklists are on the [planning tools page](https://abodeintlrealty.com/tools/).

## Developer land workplan: frequently asked questions

Is this a complete development plan?

No. It covers land due diligence and the approval path. Design, construction, marketing and sales are separate work with their own professionals.

Why does it say to ask the consultant and attorney about the environmental standard?

Liability protection can depend on the environmental assessment meeting the standard in force. A consultant and an attorney confirm what applies to your deal.

Is anything I tick saved or sent to ABODE?

No. The list runs in your browser. Ticks and choices are not saved, sent or logged. Use Copy as text or Print to keep your own copy.

## Sources and notes

1.  [Winston & Strawn, EPA approves ASTM E1527-21 as meeting All Appropriate Inquiries (effective February 13, 2023)](https://winston.com/en/winston-and-the-legal-environment/its-official-epa-approves-phase-i-standard-astm-e1527-21-as-meeting-all-appropriate-inquiry-effective-february-13-2023.html). Read October 18, 2026.